FMEA (Failure Mode and Effects Analysis) is a risk analysis method that systematically identifies the failure modes that may occur in a product or production process, their effects and causes before they happen, prioritises them by risk and defines preventive actions.
- There are two main types: DFMEA (design) and PFMEA (process).
- The classic risk measure is RPN = Severity (S) × Occurrence (O) × Detection (D); each 1–10.
- The AIAG-VDA 2019 handbook uses Action Priority (AP: High/Medium/Low) instead of RPN.
- Its output becomes input for the control plan and work instructions.
- It is used in automotive (IATF 16949, APQP), aerospace, medical and general manufacturing.
What Is FMEA?
FMEA answers the question “how can this product/process fail?” in a table. Each row is a function and one failure mode of that function. For each failure mode, the effect (what does the customer experience?), the cause (why does it happen?) and current controls (prevention and detection) are written down; then the risk is scored and actions are defined for high-risk rows. The method was born in the US military in the 1940s and became one of the mandatory quality tools of the automotive industry.
DFMEA and PFMEA
- DFMEA: Done at the design stage. It addresses questions such as “Will this material soften at this temperature?” and “Will this tolerance make assembly harder?”.
- PFMEA: Done on the process flow chart. For each operation, the question is “what happens if it is done incompletely, wrongly or late?”. It is the type most often used by production plants.
How Is Risk Scored?
| Factor | Question | 1 | 10 |
|---|---|---|---|
| Severity (S) | If the failure happens, how serious is its effect? | Not noticeable | Safety/legal, without warning |
| Occurrence (O) | How often does the cause arise? | Very rare | Almost inevitable |
| Detection (D) | Do current controls catch the failure before it reaches the customer? | Certainly catches | Cannot catch |
In the classic method, RPN = S × O × D is calculated and action is taken on rows above a certain threshold (for example 100). The AIAG-VDA 2019 handbook changed this approach: S=10, O=2, D=5 (RPN 100) and S=2, O=5, D=10 (RPN 100) give the same number, but the first carries a safety risk. That is why an Action Priority (AP) table based on the combination of the three factors is used; Severity always dominates and cannot be reduced, but O (prevention) and D (detection) can be improved.
How Is FMEA Done?
- Define the scope: Which product, which process steps, which team.
- Extract the structure and functions: What each operation must do (“hold the outer diameter at 5.00 ± 0.10 mm”).
- List the failure modes: The opposite of the function: diameter too large, too small, fluctuating.
- Write the effect and cause: Effect: the cable does not fit the connector. Cause: the extruder speed is not constant.
- Enter current controls: Prevention (speed control loop) and detection (hourly diameter measurement).
- Score and prioritise.
- Define actions, implement them and re-score.
- Update the control plan. See What Is a Control Plan?
Common Mistakes
- FMEA filled in by one person at a desk; without shop-floor knowledge, Occurrence and Detection scores are guesses.
- “Adjusting” scores to bring them below the threshold.
- Writing “operator will be trained” in the action column; this never permanently lowers the D or O score.
- Never opening the file again after PPAP; an FMEA not fed with real downtime and scrap data becomes outdated.
- Not keeping it in sync with the control plan.
Frequently Asked Questions
What is the difference between DFMEA and PFMEA?
What is RPN and how is it calculated?
When should FMEA be done?
FMEA in EFFIX MES
EFFIX MES is not FMEA software; it provides data for FMEA’s weakest point, the question “are the Occurrence and Detection scores based on real data?”. Downtime and failure history, scrap records, SPC control charts and non-conformance (NCR) records show how often each failure mode actually occurs and whether current controls catch it. Controls derived from the FMEA are defined in EFFIX as control plans and quality tasks, and deviations are monitored with the Proactive Alert System. To feed your FMEA with data from the shop floor, see the EFFIX MES page or request a demo.