What Is SMED? How Can Setup Time Be Reduced?

What Is SMED? How Can Setup Time Be Reduced?

SMED is a lean manufacturing method that aims to systematically reduce the preparation time needed for a model or product changeover on a machine. It stands for Single Minute Exchange of Die; the goal is to bring setup time down to single-digit minutes. The method is based on separating setup steps into those done while the machine is stopped and those that can be done while it is running, and moving as much work as possible into the second group.

In brief

  • SMED = Single Minute Exchange of Die; the goal is a setup time under 10 minutes.
  • Setup time = the time between the last good part and the first good part of the new product.
  • Key distinction: internal setup (machine stopped) and external setup (machine running).
  • Shorter setups directly raise the availability component of OEE and make small-batch production possible.
  • Users: production engineers, planning, maintenance and shop-floor teams.

Why does it matter?

When setup times are long, the factory defends itself by running large batches. Large batches mean more work in process, longer lead times and slower response to orders. When setup gets shorter, more model changes can be made on the same machine in a day; the plan becomes more flexible and stock falls.

The second effect is on measurement. In most factories model changes are recorded as planned downtime and pull down availability in the OEE calculation. Every minute of setup time is capacity opened up directly for production.

SMED implementation steps

  1. Measure the current state. Record a model change from start to finish. Write down each step, its duration and who does it. Video recording is the most reliable method.
  2. Separate internal and external setup. For each step on the list a single question is asked: can this work be done while the machine is running?
  3. Move internal setup to external. Mould preheating, preparing fixtures and bolts and setting adjustment values in advance are typical examples of this step.
  4. Speed up the remaining internal setup. Quick-connect fittings, moulds at standard heights, one-touch locks, cams and clips instead of bolts.
  5. Eliminate adjustment and trial parts. Trial parts are often the biggest item in setup time. Recorded settings per product and positioning fixtures eliminate this item.
  6. Standardise. If the new method does not become a work instruction, the time returns to its old level within a few weeks.

Typical setup losses

LossCauseDirection of solution
SearchingFixtures and spanners not in placeSetup cart, shadow board, 5S
WaitingForklift or crane not arrivingExternal setup plan, preparation before the call
Trial partsSettings kept in memoryRecorded parameters per product
Re-adjustmentNo positioning referenceMechanical stops, graduated scales

Common mistakes

  • Measuring only the mould change. If adjustment and trial time are left out, improvement stays on paper.
  • Investing first. Most SMED gains come from organisation and sequencing changes; external setup should be organised before switching to a hydraulic mould clamping system.
  • One-off effort. Improvement does not last unless the time is recorded.
  • Treating setup as maintenance work. A model change should be planned as a production process and written into the plan.

Measurement and follow-up

For SMED work to be sustainable, the duration of every model change should be recorded automatically. When the setup stop derived from machine status is kept together with information on which product was changed to which, a setup matrix by product pair emerges. This matrix is used both to sequence similar products back to back in scheduling and to improve the most expensive changeovers first.

Frequently Asked Questions

What does SMED stand for?
SMED stands for Single Minute Exchange of Die. The aim is to complete a model change in single-digit minutes, that is, under 10 minutes. The method was systematised by Shigeo Shingo.
What is the difference between internal and external setup?
Internal setup is work that can only be done while the machine is stopped, such as removing and fitting the mould. External setup is preparation that can be done while the machine is running, such as bringing the mould to the area and preparing fixtures and materials. The essence of SMED is moving internal setup work to external setup.
From when is setup time measured?
Setup time is the time from the moment the last good part of the previous order comes out until the first good part of the new order comes out. Trial parts and repeated adjustments are included in this time; if only the minutes of the mould change are measured, the time appears shorter than it is.

SMED in EFFIX MES

EFFIX MES records model changes automatically through downtime records and reasons, so setup time relies on data collected from the shop floor rather than estimates. Setup stops are reflected in the availability component of OEE and can be examined by machine, shift or product on downtime analysis screens. On the scheduling side, the Gantt view and rule-based scheduling support sequencing jobs in an order that reduces setup cost. Mould and tool life and mounting/dismounting tracking monitor how long each mould stays on which machine. For more information, see the EFFIX MES page or request a demo.