
What Is Order Due Dating (Order Promising)?
Order due dating is the work of calculating on which date a customer order can be delivered by evaluating stock, capacity and material availability together. The aim is for the promise made by sales to match production reality. Well-designed due dating reduces both delays and unnecessary early production.
- Question: what is the earliest realistic date this order can be delivered?
- ATP: looks at stock and planned receipts. CTP: also takes capacity and materials into account.
- The calculation relies on three inputs: material availability, capacity load, operation times.
- The due date given must be recorded; revisions should be tracked separately.
- Core benefit: on-time delivery becomes measurable and improvable.
How Is a Due Date Calculated?
- Stock check: can the demand be met from existing finished goods stock?
- Material check: if not, when will the required raw material be ready?
- Capacity check: on which resources, and when, will the required operations find a slot?
- Backward/forward scheduling: the finish date is found by adding operation times and setups.
- Logistics time: shipment preparation and transport time are added.
If any of these steps is skipped, the due date comes out systematically optimistic. The most frequently skipped step is the capacity check, because it is the most laborious.
Factors That Undermine Due Date Reliability
| Factor | Consequence |
|---|---|
| Infinite capacity assumption | Several jobs are promised in the same week |
| Outdated cycle times | Production takes longer than planned |
| Unplanned downtime not accounted for | Every breakdown turns directly into a delay |
| Rush orders squeezed in | Existing due dates slip silently |
| Scrap rate ignored | Quantity falls short, an extra run is needed |
How Should Rush Orders Be Managed?
Rush orders are unavoidable; the problem is not accepting them but accepting them without seeing their impact. The right approach is to first calculate the impact of the inserted job on other orders’ due dates, and then decide. Scenario comparison helps here: the sentence “if we insert this job today, three orders slip by two days” makes the decision data-based.
Common Mistakes
- Sales setting the due date alone. Dates given without production’s view are often missed.
- Not keeping the first due date. If revisions overwrite it, performance measurement loses its meaning.
- Everyone adding their own buffer. Total lead time grows unnecessarily.
- Basing material due dates on the supplier’s promise. Past performance data is more reliable.
- Not analysing deviations. If the root causes of delays are not separated, the same mistake repeats.
Breaking Delays Down by Root Cause
The fastest way to improve due date reliability is to separate late orders by cause instead of throwing them into a single “late” box. In practice, delays fall under a few headings: material arrived late, the machine broke down, a quality problem required re-production, a rush order was inserted, the cycle time estimate was wrong, or the order was given an unrealistic date in the first place. Keeping this breakdown for three months shows in most factories that most delays come from a single cause; focusing on that cause brings more benefit than changing the due dating algorithm.
Frequently Asked Questions
What is the difference between ATP and CTP?
How is due date reliability measured?
Should I leave a buffer when giving a due date?
Order Due Dating in EFFIX MES
In the EFFIX MES planning module, order due dating works on the same data as capacity analysis and scheduling; machine, mould and labour constraints go into the due date calculation. Thanks to work order management and the container/batch plan, which batches will fulfil an order can be tracked. Scenario simulation shows the impact of inserting a rush order on existing due dates before applying it. Actual production and downtime data from the production monitoring module make it possible to report whether given due dates were met; with the flexible report designer, the on-time delivery indicator can be tracked in your own breakdowns. For more, see the EFFIX MES page or request a demo.
