What Is MRP?

What Is MRP?

MRP (Material Requirements Planning) is the planning method that starts from the production plan and the bill of materials to calculate how much of which material is needed and when. It subtracts stock on hand and open orders, and generates order or production proposals by shifting the remaining net requirement back by the lead time.

In brief

  • Inputs: production plan, bill of materials (BOM), stock balance, open orders, lead times.
  • Output: timed purchasing and production proposals.
  • Core calculation: gross requirement − stock on hand − scheduled receipts = net requirement.
  • Classic MRP assumes infinite capacity ; it does not look at machine load.
  • Core benefit: stoppages caused by material shortages decrease and excess stock is brought under control.

How Does MRP Calculate?

MRP resolves the bill of materials from top to bottom. It starts from the finished product, multiplies the sub-component requirement at each level and shifts it back by that level’s lead time. This is called “explosion”.

StepCalculation
Gross requirementParent-level requirement × BOM quantity
Net requirementGross requirement − stock on hand − scheduled receipts
Order timeRequirement date − lead time

Example: if 4 screws are needed per unit for 1,000 units, the gross requirement is 4,000. If there are 1,500 in stock and 500 are shown as in transit, the net requirement is 2,000. If the screw’s lead time is 10 days, the order must be placed 10 days before the requirement date.

Strengths and Weaknesses of MRP

  • Strength: it performs in seconds a calculation that could not be done by hand for multi-level bills of materials.
  • Strength: it spreads requirements over time and breaks the habit of bulk ordering.
  • Weakness: it does not see capacity; the machine may be full on the date it proposes.
  • Weakness: it is extremely sensitive to data. A single wrong BOM line breaks the whole chain.
  • Weakness: it assumes fixed lead times; in reality lead times change with load.

Common Mistakes

  1. Not keeping the BOM up to date. When an engineering change is not entered into the system, MRP orders the old part.
  2. Not measuring stock accuracy. If count accuracy is low, MRP relies on phantom stock and opens short orders.
  3. Entering optimistic lead times. Use the supplier’s realistic time, not the average.
  4. Not accounting for scrap and waste. If operation scrap is not defined in the BOM, the requirement always comes out short.
  5. Applying MRP output without question. Proposals should go through the planner’s review.

The Relationship Between MRP and MES

MRP usually runs on the ERP side and looks at the planning horizon. The MES knows in real time what happens on the shop floor: actual consumption, actual scrap, actual completion. Connecting these two worlds directly improves MRP accuracy, because the stock and consumption data feeding MRP becomes a measurement rather than an estimate.

Lot Sizing Rules

After MRP finds the net requirement, it converts it into an order quantity, and this is where the lot sizing rule comes in. The three most common approaches are: ordering exactly the requirement (lot-for-lot), fixed lot size and minimum order quantity. If the supplier imposes a minimum quantity, or a mould produces a set number of parts per cycle, the rule must follow that. When the wrong lot rule is chosen, MRP either generates needlessly small orders or fills the warehouse with months’ worth of material.

Frequently Asked Questions

What is the difference between MRP and MRP II?
MRP only calculates material requirements. MRP II adds capacity, labour and financial dimensions to this calculation, aiming to plan all production resources. The planning core of today’s ERP systems largely relies on MRP II logic.
Does MRP take capacity into account?
Classic MRP assumes infinite capacity; when calculating requirements it does not check whether machines are full. To account for capacity constraints, finite-capacity scheduling (APS) or a separate capacity planning step is needed.
What does MRP need to work correctly?
Three things are critical: a correct bill of materials, an up-to-date stock balance and realistic lead times. If any one of these is broken, MRP systematically proposes wrong orders. At the root of most MRP complaints lies data quality, not the algorithm.

MRP in EFFIX MES

The MRP calculation classically runs on the ERP side; EFFIX MES keeps the shop-floor data this calculation relies on accurate and current. BOM, routing, variant/recipe and unit conversion definitions can be managed within EFFIX; material consumption, scrap and work in process (WIP) are recorded in real time. Through ERP integration (SAP, IFS, Netsis and a generic adapter), production and scrap confirmations are passed to the ERP, so MRP works with measured rather than estimated consumption. On the planning side, work order management, capacity analysis and order due-dating turn MRP output into an executable schedule. For details, see the EFFIX MES page or request a demo.