What Is Capacity Planning?
Capacity planning is the process of calculating whether the machine, mould, personnel and shift resources available in a given period are sufficient to meet demand. Its purpose is to make a capacity shortfall or surplus visible before committing to orders. The result usually leads to one of three decisions: accept the demand, increase resources or rearrange due dates.
- Core question: can the incoming load be done with the available resources in the given time?
- Rough-cut capacity: long horizon, main resources. Detailed capacity: short horizon, operation level.
- Capacity is not just machines: moulds, operator skills and the shift calendar are constraints too.
- Calculations should be based on effective capacity , not theoretical capacity.
- Key benefit: realistic due-date promises and lower emergency subcontracting costs.
Types of Capacity
| Type | Definition | Use |
|---|---|---|
| Theoretical capacity | Assumes uninterrupted running | Upper-limit reference |
| Effective capacity | Breaks, setup and maintenance deducted | The basis of planning |
| Actual capacity | What was really produced in the past | Verification and calibration |
The gap between the three should be tracked deliberately. If actual capacity is far below effective capacity, the problem is not in planning but in losses; downtime analysis should come into play.
A Simple Calculation
You can calculate a machine’s weekly capacity like this:
- Calendar time: 7 days × 24 hours = 168 hours
- Shift plan: 5 days × 2 shifts × 8 hours = 80 hours (available time)
- Planned maintenance and breaks: −6 hours → 74 hours
- Effective capacity assuming a historical OEE of 70%: 74 × 0.70 ≈ 52 hours’ worth of production
- If cycle time is 2 minutes/piece: 52 × 60 ÷ 2 ≈ 1,560 pieces
This number is the realistic baseline to use when accepting orders. If the number of moulds or certified operators sets a lower limit, that limit is the real capacity.
Rough-Cut and Detailed Capacity Checks
- Rough-cut capacity (RCCP): looks only at critical resources, works on a monthly/weekly horizon and supports order acceptance.
- Detailed capacity (CRP): considers all operations and routings, works hand in hand with scheduling and supports daily decisions.
The two levels feed each other: a conflict not visible at the rough-cut level shows up at the detailed level; a recurring squeeze at the detailed level shows that an assumption at the rough-cut level is wrong.
Common Mistakes
- Promising based on theoretical capacity. The plan slips from the first week and trust is lost.
- Ignoring setup time. In high-mix production, setup time eats up a significant share of capacity.
- Looking only at machines. In most factories, mould and operator constraints kick in before machines.
- Assuming an average product. When the product mix changes, hourly output changes; a calculation with a single average is misleading.
- Calculating capacity once and leaving it. Shift patterns, staff and the machine park change; if the calculation is not refreshed, it goes out of date.
Frequently Asked Questions
What is the difference between theoretical and effective capacity?
Is OEE used in capacity calculations?
How often should capacity planning be done?
Capacity Planning in EFFIX MES
EFFIX MES handles capacity analysis across machine, mould and human dimensions together, so it becomes visible which one is the real constraint. Because shift management and planned maintenance windows are reflected in the calendar, available time is calculated realistically. Thanks to OEE, availability and cycle time data from the production monitoring module, capacity assumptions can be compared with actual performance. With scenario simulation, the effect of an extra shift or using an alternative resource can be tested; order due-date promising works on this capacity. For details, see the EFFIX MES page or request a demo.