Finite and Infinite Capacity Planning
Finite capacity planning is a planning approach that places jobs on the time axis without exceeding the real capacity limits of machines and resources. Infinite capacity planning, by contrast, assumes resources are unlimited and positions jobs simply by counting back from the due date. The difference between the two approaches is the key distinction that determines whether a plan holds up on the shop floor.
- Infinite capacity: resource limits are ignored and jobs are placed backwards from the due date.
- Finite capacity: machine, mould, labour and calendar constraints are taken into account.
- MRP classically works on infinite capacity logic, while APS works on finite capacity logic.
- For finite capacity to produce correct results, it requires routings, standard times, setup times and the shift calendar.
- Users: production planners, the scheduling team, and sales and order promising functions.
How does infinite capacity planning work?
In the infinite capacity approach, the system asks: when should each operation start in order to deliver this order on time? The duration of every operation is known, and operations are sequenced backwards from the due date. If two jobs land on the same machine at the same hour, the system does not object.
The output of this approach is a requirements table: how much workload falls into which week. It is sufficient for material requirements and purchasing. However, when the load profile of the output is examined, you often see twice the capacity in some weeks and gaps in others. Correcting that picture is left to the planner.
How does finite capacity planning work?
In finite capacity, every resource behaves like a calendar. When an operation is to be placed, the system checks whether that machine is free in that interval; if it is occupied, the operation is pushed to the first available slot. The result is a workable schedule with no overlaps.
The main gain of this approach is a realistic due date. When an order is entered, it can be added on top of the existing load to calculate when it will be finished. In return, the model demands more data and more discipline.
Comparison
| Criterion | Infinite capacity | Finite capacity |
|---|---|---|
| Resource limit | Ignored | Taken into account |
| Typical use | MRP, material plan | APS, shop floor schedule |
| Calculation time | Short | Longer |
| Data requirement | Low | High |
| Due date reliability | Low | High |
| Overlaps | Possible | None |
Which one, and when?
- Long-term material and purchasing plan: infinite capacity is sufficient.
- Weekly and daily shop floor schedule: finite capacity is required.
- Promising a date to the customer: the simulation should be run on finite capacity.
- Lines with heavy bottlenecks: finite capacity is essential; a single constraint determines the entire flow.
Points to watch when making the transition
Moving to finite capacity is a data project more than a software installation. Routings must be updated first, and operation times compared with actual values measured on the shop floor. In most factories, setup times are either not defined at all or entered as a single average value; changeover times that depend on the product pair improve the quality of the plan considerably.
The second issue is constraint selection. Putting every constraint into the model at once makes the plan rigid, and the schedule falls apart at every small deviation. It is usually best to start with machine and mould constraints, adding the skilled operator constraint as the skills matrix matures.
The third is feedback. A finite capacity plan drifts away from reality from day one unless actual start and finish times come back from the shop floor. For the plan to stay alive, production monitoring data must flow back into the schedule.
Frequently Asked Questions
Why is infinite capacity planning still used?
What data does finite capacity planning require?
Is a finite capacity plan always better?
Finite and Infinite Capacity Planning in EFFIX MES
In its planning and scheduling module, EFFIX MES provides capacity analysis that assesses machine, mould and labour capacity together. Work orders are followed in the Gantt and Kanban views; with manual and rule-based scheduling, jobs can be sequenced within capacity limits. Scenario simulation makes it possible to see how the due date would change if an order were added to the existing load, before the plan goes live. Because production monitoring data is collected in the same system, the schedule is updated with actual starts and finishes from the shop floor. For details, see the EFFIX MES page or submit a demo request.