What Is Throughput?

What Is Throughput?

Throughput is the quantity of good product a machine, line or factory produces per unit of time; it is expressed in units such as pieces/hour, tonnes/day or metres/shift. According to the Theory of Constraints, the throughput of a system is determined by its slowest resource, the bottleneck; the speed of the other machines does not change the result.

In brief
  • Formula: Throughput = Good Output / Time (pieces/hour, tonnes/day, etc.)
  • System throughput = the throughput of the bottleneck
  • Little's Law: Throughput = WIP / Lead Time
  • Users: production and planning management, plant managers
  • Core benefit: shows the factory's real output capability in a single figure

What Is Throughput?

OEE tells you how efficiently a machine runs; throughput tells you how much product comes out at the end of the system. The two do not always move in the same direction: the OEE of a machine that is not the bottleneck can rise to 90% without the factory's throughput increasing by a single unit, because the products pile up in front of the next bottleneck. Throughput is therefore a more direct outcome indicator than OEE at factory level.

On the accounting side, the Theory of Constraints also defines throughput in monetary terms: sales revenue minus totally variable costs. This article focuses on physical throughput.

Why Does It Matter?

  • Directly linked to revenue: what can be sold equals throughput; intermediate product accumulating in stock is not revenue.
  • It guides investment decisions: only investment in the bottleneck increases throughput. Investment elsewhere may be waste.
  • It is tied to lead time: by Little's Law, if throughput increases with the same WIP, lead time shortens.
  • It is the basis of due date estimates: on a line with a throughput of 400 units a day, an order of 2,000 units takes at least 5 days; promising a date without knowing this is not an estimate.

How Is It Measured?

  1. Define the measurement point: throughput should be measured at the end of the line, where the product going to the customer is counted; counts at intermediate stations are intermediate output, not throughput.
  2. Count only good product: scrap and parts to be reworked are excluded.
  3. Choose a consistent period: shift, day, week. Short windows fluctuate; daily and weekly trends are sounder for decisions.
  4. Take the product mix into account: if different products have different cycle times, unit-based throughput is misleading; standard hours or weighted units can be used.

Example

A line with three stations: cutting at 120 units/hour, welding at 80 units/hour and assembly at 100 units/hour. The throughput of the line is at most 80 units/hour (welding is the bottleneck). Raising cutting to 150 does not change throughput; it causes 70 units an hour to pile up in front of welding. Raising the OEE of welding from 75% to 90%, on the other hand, increases throughput by around 20%.

How Do You Increase Throughput?

  • Never leave the bottleneck idle: every minute lost at the bottleneck is lost by the whole factory. Keep it running even during breaks and place a buffer in front of it.
  • Put quality ahead of the bottleneck: a part scrapped after the bottleneck is the most expensive scrap; carry out the inspection before the bottleneck.
  • Shorten setups at the bottleneck: SMED creates the most value here.
  • Take non-bottleneck work off the bottleneck: some operations can be moved to another machine or an external supplier.
  • Look again when the bottleneck moves: once one bottleneck is resolved, another resource becomes the bottleneck; the process is cyclical.

Common Mistakes

  • Trying to raise OEE on every machine; outside the bottleneck this only creates work in process.
  • Including defective parts in throughput.
  • Identifying the bottleneck by guesswork; the resource where the queue builds up most and that stays busy longest should be found from the data.

Frequently Asked Questions

How is throughput calculated?
Throughput = Good Output / Time. For example, if 1,800 good units were produced in a shift, the throughput is 225 units/hour. Defective parts are not included; what is measured is the output going to the customer.
What is the difference between throughput and capacity?
Capacity is the maximum quantity the line could produce under ideal conditions; throughput is what it actually produces. The difference comes from downtime, speed loss, defects and waiting at the bottleneck. Throughput can never exceed the capacity of the bottleneck.
How can throughput be increased?
Find the bottleneck and improve it first: make sure it is never idle, place a buffer in front of it, and reduce its setups and downtime. Speeding up machines other than the bottleneck does not increase throughput; it only creates work in process.

Throughput in EFFIX MES

EFFIX MES collects production quantities in real time from machine counters and the HMI terminal, deducts scrap records and reports good output by machine, line, shift and work order. Capacity analysis and the Gantt view show which resource is busy and where work is accumulating in front of it; the work in process (WIP) screen reveals where waiting builds up. Scenario simulation makes it possible to test, at the planning stage, the effect on output of adding a shift at the bottleneck or assigning an alternative routing. For more information, see the EFFIX MES page or send a demo request.