What Is TEEP? How It Differs from OEE

What Is TEEP? How It Differs from OEE

TEEP (Total Effective Equipment Performance) is an indicator that shows how much valuable production a machine carries out over the entire calendar time (7 days × 24 hours). It uses the same three components as OEE, but also counts the hours in which no production is planned as a loss; it therefore reveals the hidden capacity of the machine.

In brief
  • Formula: TEEP = OEE × Utilization
  • Utilization = Planned Production Time / Calendar Time
  • Unit: percentage; TEEP is always equal to or lower than OEE
  • Users: plant managers, investment and capacity planning leads
  • Core benefit: provides data for the question "a new machine, a new shift, or an OEE improvement?"

What Is TEEP?

The denominator of OEE is planned production time: weekends, the third shift and hours with no production plan are excluded from the outset. TEEP removes that distinction. Since the machine exists for 168 hours a week, it looks at how much of those 168 hours was spent producing good parts. The difference is a fourth multiplier called the utilization rate.

Put differently, OEE answers "how well do we run the machine when we run it", while TEEP answers "how much do we run the machine, and how well do we run it".

Why Does It Matter?

  • It clarifies the investment decision: a machine with 80% OEE but running a single shift has a TEEP of around 27%. If capacity is short, the answer may be a second shift rather than a new machine.
  • It shows the real cost of capacity: depreciation and rent run over 168 hours; if the machine earns money for 40 of them, unit cost should be calculated accordingly.
  • It is a compass in demand fluctuations: when orders rise, it quickly shows how much calendar capacity is left.

How Is TEEP Calculated?

StepValue
Calendar time (1 week)168 hours
Planned production time (5 days × 2 shifts × 7.5 hours)75 hours
Utilization75 / 168 = 44.6%
OEE (measured)70%
TEEP0.446 × 0.70 = 31.3%

This machine uses roughly a third of its potential. When capacity needs to increase, a third shift (utilization rises to 67%, TEEP to 47%) and OEE improvement should be assessed first; a new machine should be left until last.

OEE and TEEP Compared

OEETEEP
DenominatorPlanned production timeCalendar time (7×24)
QuestionHow efficient are we while running?How much of the total potential are we using?
OwnerProduction, maintenance, qualityPlant management, planning
Target85% is widely acceptedDepends on the operating pattern; no universal threshold
Decision areaReducing downtime, speed loss and defectsShift patterns, investment, outsourcing

Common Mistakes

  • Targeting TEEP as if it were OEE: targeting 85% TEEP in a single-shift plant is meaningless; if there is no demand, running the machine is waste.
  • Excluding planned maintenance from the denominator: nothing is excluded from the denominator in TEEP; planned maintenance and holidays are losses too. This is not "bad", it is simply information.
  • Looking at a single machine: raising the TEEP of a machine that is not the bottleneck creates inventory. TEEP is most meaningful on the bottleneck machine.

Frequently Asked Questions

What is the difference between TEEP and OEE?
OEE is calculated against planned production time; TEEP against the entire calendar time (7×24). OEE shows how efficient the machine is while it is being run, TEEP how much of the machine's total potential is being used.
When should TEEP be used?
Before a decision to buy a new machine or add a shift. A low TEEP shows there is unused calendar capacity on the existing machine; a shift adjustment or an OEE improvement may be cheaper than an investment.
Is there a target value for TEEP?
There is no established threshold such as the 85% used for OEE. TEEP depends entirely on the operating pattern: 30% is normal in a single-shift plant, while above 80% is expected in a continuous process running 7×24.

TEEP in EFFIX MES

By combining the working calendar defined in shift management with the actual running data collected from the machine, EFFIX MES makes it possible to track utilization alongside OEE. The capacity analysis module shows machine, mould and labour capacity on the calendar; with scenario simulation, the effect of questions such as "what if we add a third shift" or "what if we run this machine at the weekend" can be tested on the planning screen. The results are compared by machine and period in dashboards and pivot reports. For more information, see the EFFIX MES page or send a demo request.