What Is OOE?
OOE (Overall Operations Effectiveness) is an indicator showing how productively a machine produces over its entire shift or operating time. It differs from OEE in that it also counts planned stops, such as breaks and planned maintenance, as losses; it differs from TEEP in that it does not take into account hours with no production plan (closed shifts, weekends).
- Formula: OOE = Availability’ × Performance × Quality; where Availability’ = Run Time / Total Operating (Shift) Time
- Ranking: TEEP ≤ OOE ≤ OEE
- Shows planned stops (breaks, planned maintenance, meetings) as losses
- Users: operations manager, shift planning staff
- Key benefit: makes you question whether planned stops are really necessary
What Is OOE?
The three indicators in the OEE family calculate the same three components (availability, performance, quality) with a different denominator. As the denominator widens, more time appears as “loss”:
| Indicator | Denominator | Planned time counted as loss |
|---|---|---|
| OEE | Planned production time | None |
| OOE | Total operating time (shift time) | Breaks, planned maintenance, meetings, cleaning |
| TEEP | Calendar time (7×24) | The above + closed shifts, holidays, weekends |
The definition of OOE is not as standardised in the literature as OEE and TEEP; some sources take shift time as “total operating time”, others the time the machine is kept switched on. It is enough to decide once which definition you will use in the factory and keep it fixed.
Why Does It Matter?
The most criticised aspect of OEE is that it makes planned stops invisible. A 20-minute meeting at the start of the shift, a 45-minute meal break and 2 hours of planned maintenance every week do not affect OEE at all, because they are all left out of the denominator as “planned”. Yet this time is also machine capacity, and much of it can be shortened or shifted:
- Does the machine have to stop during the meal break, or can operators go in rotation?
- Is planned maintenance done during production hours, or can it be done between shifts?
- Can the start-of-shift meeting be held while the machine is running?
OOE puts numbers on these questions. If a machine with 78% OEE has an OOE of 64%, 14 points of the loss sit in time hidden behind the “planned” label.
Sample Calculation
- Shift time 480 min. Planned stops: 45 min meal + 15 min meeting = 60 min. Planned production time 420 min.
- Unplanned downtime 60 min → run time 360 min.
- Let performance be 90% and quality 98%.
- OEE: (360/420) × 0.90 × 0.98 = 0.857 × 0.882 = 75.6%
- OOE: (360/480) × 0.90 × 0.98 = 0.75 × 0.882 = 66.2%
The 9.4-point difference is the cost of planned stops. In this shift, running the machine in rotation during the meal break does not change OEE but directly raises OOE, because OEE does not see this improvement.
Which Indicator Should Be Used When?
- Production and maintenance team → OEE: The losses they can control are breakdowns, setup, speed and defects.
- Operations management → OOE: Break patterns, maintenance windows and meeting times are their decisions.
- Plant management → TEEP: The number of shifts, weekend working and investment are their decisions.
Giving each level the indicator within its own area of control ends the “OEE is low but it’s not in our hands” debate.
Common Mistakes
- Mixing OOE and OEE in the same report without stating which denominator each is calculated with.
- Cutting maintenance when planned maintenance shows up as a loss in OOE. The aim is not to cancel maintenance but to move it to non-production time.
- Benchmarking OOE against 85% too. The 85% reference is for OEE.
Frequently Asked Questions
What is the difference between OOE and OEE?
When is OOE preferred?
Should the three indicators be tracked together?
OOE in EFFIX MES
In EFFIX MES, stops are recorded as planned or unplanned together with their reasons; in the shift management module, break and planned maintenance windows are defined in the shift calendar. This way, OEE and availability values that include planned stops can be reported separately from the same data set. The no-code report designer and pivot reports make it easy to show the share of planned stops in total loss per machine and shift. For details, see the EFFIX MES page or request a demo.