What Are the Six Big Losses?

What Are the Six Big Losses?

The Six Big Losses is a classification model from Total Productive Maintenance (TPM) that divides the losses lowering a machine’s OEE into six categories: breakdowns, setup and adjustment, minor stops, reduced speed, scrap during production and startup losses. Every two losses correspond to one OEE component, so a drop in OEE can be tied to a concrete cause.

In brief

  • Availability losses: 1) breakdowns and unplanned stops, 2) setup and adjustment
  • Performance losses: 3) minor stops and idling, 4) reduced speed
  • Quality losses: 5) scrap/rework during production, 6) startup (first-part) losses
  • Users: TPM and continuous improvement teams, production and maintenance managers
  • Key benefit: turns OEE from diagnosis into action

What Are the Six Big Losses?

OEE gives a machine’s efficiency as a percentage, but you cannot act on a percentage. To raise OEE from 65% to 75%, you need to know which loss occurs where. The Six Big Losses model does exactly that: it splits each OEE component into two concrete types of loss. The model was defined in Japanese TPM literature in the 1980s and is still the standard framework for OEE analysis today.

The Six Losses One by One

#LossOEE componentTypical example
1Breakdowns and unplanned stopsAvailabilityMotor failure, sensor fault, waiting for material
2Setup and adjustmentAvailabilityDie change, program loading, first-part approval
3Minor stops and idlingPerformancePart jams, sensor hang-ups, short feeds
4Reduced speedPerformanceSlowing down due to worn tools or poor raw material
5Scrap during productionQualityOut-of-tolerance parts, surface defects, rework
6Startup lossesQualityDefective parts during warm-up, trial runs after setup

1. Breakdowns and unplanned stops

The machine stopping unexpectedly. It is usually the most visible loss because everyone notices it. It is measured by downtime duration and frequency, and analysed further with MTBF and MTTR. It is reduced through planned and predictive maintenance.

2. Setup and adjustment

The time spent changing from one product to another: from the last good part to the first good part of the new product. In high-mix production it can be the largest loss. It is reduced with SMED.

3. Minor stops and idling

Hang-ups usually shorter than a few minutes that the operator does not record. Small one by one, large in total, and the least measured loss. It is derived from counter data: unexpected gaps between cycles.

4. Reduced speed

The machine is running but slower than the ideal cycle time. The cause may be tool wear, raw material differences or a lower speed the operator considers “safe”. It is measured as the ratio of actual cycle time to ideal cycle time.

5. Scrap and rework during production

Defective parts produced during stable production. A reworked part is also a loss. It is measured by scrap rate and FPY, and reduced with SPC and the control plan.

6. Startup losses

Defective parts produced while the machine warms up, after setup or at the start of a shift until it reaches a stable state. It matters in processes such as injection moulding, extrusion and painting, and often goes unmeasured because most factories consider it “normal”.

How Is It Applied?

  1. Map every downtime reason to one of the six categories. If the downtime code list does not fit this structure, fix the list.
  2. Convert losses to time. Instead of percentages, “14 hours of setup, 9 hours of breakdowns and 6 hours of minor stops this week” is clearer for decisions.
  3. Do a Pareto analysis. Usually two losses make up most of the total; start there.
  4. Link each loss to the right tool. Breakdowns → maintenance plan; setup → SMED; minor stops → root cause and sensor fixes; speed → cycle time standard; scrap → SPC; startup → parameter standard.
  5. Keep the measurement constant and track the trend.

Common Mistakes

  • Not measuring minor stops and startup losses; as a result the loss looks smaller than it is.
  • Counting setup as planned downtime and excluding it from OEE; the second loss disappears from reports.
  • Focusing only on breakdowns; the most visible loss is not always the biggest.

Frequently Asked Questions

Which OEE components do the Six Big Losses correspond to?
Breakdowns and setup are availability losses; minor stops and reduced speed are performance losses; scrap during production and startup losses are quality losses. Each component carries two losses.
Which loss should you start with?
The biggest in terms of time, but only if the measurement is reliable. In most factories breakdowns and setup look biggest, while minor stops look small because they are not measured. First you need to see the real distribution with automatic data collection.
Do the Six Big Losses apply only to machines?
The model was designed with equipment in mind, but it is also applied on manual lines. Losses such as operators waiting or missing material are usually put in the downtime category, and slowdowns in manual work in the performance category.

The Six Big Losses in EFFIX MES

In EFFIX MES, downtime reasons are coded on dynamic definition screens and each code is linked to categories such as planned/unplanned or breakdown/setup; stops start automatically from the machine, and the operator selects the reason on the HMI terminal. Minor stops are captured from counter and machine signals, speed loss is compared with the ideal value on cycle time screens, and scrap and rework records are linked to the quality component. As a result, the six losses can be seen as a time-based Pareto in pivot reports and dashboards from the same database. The Proactive Alert System sends a notification when one of these losses crosses a threshold, using its downtime, efficiency and quality detectors, and opens a maintenance work order if needed. For details, see the EFFIX MES page or request a demo.