The Three Components of OEE: Availability, Performance, Quality

The Three Components of OEE: Availability, Performance, Quality

OEE’s three components, availability, performance and quality, are ratios that break down a machine’s loss during planned production time into three separate causes: how much the machine ran (availability), how close it came to ideal speed while running (performance) and how much of its output was good (quality). OEE is the product of these three ratios.

In brief

  • Availability = Run Time / Planned Production Time
  • Performance = (Ideal Cycle Time × Units Produced) / Run Time
  • Quality = Good Units / Units Produced
  • OEE = Availability × Performance × Quality
  • Each component carries two of the Six Big Losses

Why Isn’t a Single Number Enough?

For a machine with 65% OEE, that figure tells you almost nothing. The same 65% can come from a machine that “breaks down a lot but runs fast and without defects” or from one that “never stops but runs slowly all the time”. In the first case the maintenance team should step in, in the second the process engineer. The components make this distinction.

Availability

Availability shows for how much of the planned production time the machine actually ran. The denominator is planned time; breaks and hours with no production plan are excluded from the start. Everything subtracted from the numerator is unplanned downtime: breakdowns, adjustments and mould changes (setup), waiting for material or operators.

Example: 45 min breakdown and 30 min setup in 450 min of planned time → run time 375 min → availability 83.3%.

Losses it carries: breakdowns and stops; adjustments and setup.

Note: Counting setup as planned downtime and removing it from the denominator is a common mistake. Setup is time in which the machine is expected to produce but does not, and it should stay an availability loss; otherwise the effect of SMED work does not show up in OEE.

Performance

Performance measures how much the machine produced relative to ideal speed while it was running. The ideal cycle time is the machine’s design speed for that product; not the best speed achieved in the past, but the speed it should run at.

Example: 375 min run time, ideal cycle 0.5 min/unit → theoretical 750 units; actual 660 units → performance 88%.

Losses it carries: slow running (reduced speed); micro stops and idling.

Note: Unrecorded short stops accumulate here. Forty 30-second jams are a 20-minute loss, and because they do not appear in the downtime list they remain an “unexplained speed loss”. That is why automatic capture of micro stops is a prerequisite for performance analysis.

Quality

Quality shows how much of the quantity produced was good the first time. Parts recovered through rework are also counted as defective, because what is measured is first-pass quality.

Example: 640 of 660 units good → quality 97%.

Losses it carries: scrap and rework during production; start-up (first part) losses.

Note: Start-up losses are large, especially in processes that need warming up such as injection moulding and extrusion, and are often not counted because they are considered “normal”. They should be counted; it is a loss that can be reduced.

Combining and Comparing

ComponentSample valueLost time equivalent (out of 450 min)
Availability83.3%75 min
Performance88%45 min
Quality97%10 min
OEE71.1%130 min

Converting components into time (lost minutes) is easier for managers to grasp than percentages: in this shift, 130 of 450 minutes were lost, 75 of them from stops. The priority is clear.

Frequently Asked Questions

Which of the three components is the most important?
None on its own; the lowest one is the most important. Because OEE is a product, the component that drags it down the most sets the improvement priority. In most factories, availability comes out lowest at the first measurement.
Can the performance rate exceed 100%?
Mathematically it can; this shows that the ideal cycle time has been defined wrongly (slower than real speed). When performance above 100% is seen, the ideal cycle time per product and machine should be reviewed.
How are reworked parts counted in the quality rate?
Every part that is not good the first time is counted as defective in the quality component, even if it is recovered later. The aim is to measure first-pass quality; rework is a loss.

OEE Components in EFFIX MES

EFFIX MES calculates the three components separately and reports them by machine, shift, work order and product. For availability, stops are started automatically from the machine and the operator selects the reason on the HMI; for performance, the ideal cycle time defined per product and machine is used and micro stops are captured from counter data; for quality, scrap and rework records are linked to the production quantity. On dashboards and KPI boards the components can be seen side by side and also in lost minutes. When one of the components drops below a threshold, the Proactive Alert System notifies the relevant team. For more, see the EFFIX MES page or request a demo.